Willis Island, Coral Sea · Commercial / Maintenance / HVAC
Willis Island Weather Station
Bureau of Meteorology
Ongoing
Scheduled six-monthly servicing and maintenance of essential air conditioning and mechanical systems at a remote Bureau of Meteorology facility.
Challenge: The site is around 450 km east of Cairns. Tropical heat, humidity, salt air and limited access make careful planning and preventative maintenance essential.
Solution: Cool Mech coordinates equipment, travel and on-site works for each six-monthly visit, helping keep critical systems reliable in a demanding marine environment.
- · Ongoing six-monthly servicing
- · Planned logistics for remote access
- · Dependable support for critical site systems

Palm Cove, Cairns · Commercial / Maintenance / HVAC
The Sebel Palm Cove
Accor Vacation Club
Ongoing
Ongoing maintenance and servicing across more than 200 accommodation units, resort facilities and common areas.
Challenge: A large operating resort needs reliable cooling and responsive support without unnecessary disruption to guests, staff or daily operations.
Solution: Cool Mech works closely with property management to coordinate scheduled maintenance, servicing, repairs, replacements and breakdown support across the property.
- · Ongoing support across 200-plus units
- · Planned work around resort operations
- · One team for maintenance, repairs and replacements

Cairns CBD · Commercial / HVAC
Juicy Car Rentals, Cairns CBD
Juicy Car Rentals
In progress
Supply and installation of multiple cassette air conditioning systems for a new commercial fit-out in Cairns CBD.
Challenge: The air conditioning installation must be coordinated with the wider fit-out so each system is positioned, installed and ready for the new location's opening.
Solution: Cool Mech is coordinating the cassette system installation alongside other trades, with equipment selected for reliable and efficient cooling in tropical Cairns conditions.
- · Project currently underway
- · Multiple cassette systems being installed
- · Installation coordinated with the wider fit-out

Cairns City · Commercial / HVAC
CBD office plant replacement
Staged replacement of end-of-life packaged units serving a multi-tenancy office floor plate.
Challenge: Twenty-year-old rooftop plant was failing repeatedly through the wet season, with tenants complaining of humidity and no possibility of shutting the floor down during business hours.
Solution: We staged the changeover unit by unit over three weekends, reusing serviceable ductwork, upgrading condensate drainage and adding zone control so perimeter offices stopped over-cooling the core.
- · Zero business-hours downtime during the changeover
- · Measurable reduction in after-hours breakdown call-outs
- · Tenant humidity complaints resolved

Cairns Northern Beaches · Commercial / HVAC / Maintenance
Medical centre critical cooling upgrade
New ducted system for consult rooms plus dedicated cooling for a vaccine and pathology store.
Challenge: A single system served both patient areas and temperature-sensitive storage, meaning any fault put stock at risk and left the practice unable to consult.
Solution: We separated the loads, installed a dedicated redundant unit for the storage room with temperature alarming, and rebalanced supply air across consult rooms and waiting areas.
- · Cold-chain stock protected by redundant cooling and alarms
- · Consistent temperatures across consult rooms
- · Quarterly maintenance agreement with documented reporting

Tablelands · Industrial / Refrigeration
Food processing facility refrigeration
Cool room and freezer room servicing plus condensing unit replacement during a planned shutdown.
Challenge: Production could not stop, and the existing plant was struggling to hold temperature through peak ambient conditions with high door traffic.
Solution: All works were programmed into a scheduled shutdown window. We replaced the condensing units, reworked defrost controls and fitted door seals and air curtains to reduce infiltration.
- · Temperature held through peak summer loading
- · Reduced run hours and lower energy consumption
- · Works completed inside the shutdown window

Cairns · Commercial / Maintenance
Shopping centre maintenance portfolio
Asset audit and quarterly planned maintenance across common areas and multiple tenancies.
Challenge: The centre had no asset register, inconsistent service history across tenancies and unpredictable reactive spend each quarter.
Solution: We audited and tagged every unit, built a full asset register with age and condition, then set quarterly service frequencies with digital reporting to centre management.
- · Complete asset register and replacement forecast
- · Reactive spend replaced with a predictable annual figure
- · Single reporting pack for centre management

Cairns Esplanade · Commercial / Ventilation
Commercial kitchen exhaust and make-up air
New canopy, exhaust fan and make-up air system for a restaurant fit-out.
Challenge: The original design had no make-up air provision, leaving the kitchen negatively pressurised, hot for staff and pulling conditioned air out of the dining room.
Solution: We redesigned the system with a correctly sized canopy, a roof-mounted exhaust fan with attenuation and a tempered make-up air supply, then balanced and documented the airflows.
- · Compliant, certified airflows at handover
- · Comfortable kitchen and stable dining room temperatures
- · Noise complaints from neighbouring tenancies avoided

Innisfail · Commercial / HVAC
School classroom cooling upgrade
Replacement of ageing split systems across classroom blocks during term break.
Challenge: Failing units, inconsistent classroom temperatures and a hard deadline: everything had to be finished and tested before students returned.
Solution: We pre-ordered all equipment, ran multiple crews through the break, upgraded electrical supply where required and commissioned every unit with recorded results.
- · All classrooms operational for day one of term
- · Consistent temperatures across each block
- · Simplified controls for teaching staff

Portsmith, Cairns · Industrial / Ventilation
Warehouse heat relief and ventilation
High-volume roof ventilation and targeted spot cooling for a distribution warehouse.
Challenge: Internal temperatures were regularly exceeding safe working conditions, and full air conditioning of an uninsulated shed was not commercially viable.
Solution: We modelled the heat load, installed high-volume exhaust ventilation with low-level make-up air, and added spot cooling over the pick-and-pack stations.
- · Significant drop in working temperatures at a fraction of the cost of air conditioning
- · Improved staff comfort and productivity
- · Low ongoing running costs

Cairns CBD · Commercial / HVAC / Maintenance
Plant room refurbishment
Chilled water plant room upgrade including pumps, valves and controls.
Challenge: Corroded pipework, failing pumps and a controls system nobody on site understood, in a building that could not lose cooling for more than a few hours at a time.
Solution: Works were staged to maintain partial cooling throughout. We replaced pumps and valves, re-insulated pipework, rationalised the controls strategy and trained building staff on the new interface.
- · Reliable cooling restored with redundancy in place
- · Lower pumping energy consumption
- · Building staff able to operate and monitor the plant

Trinity Beach · Commercial / Maintenance / Ventilation
Body corporate common area systems
Maintenance agreement covering lobby cooling, car park ventilation and amenities exhaust.
Challenge: The committee had no service history, recurring car park ventilation faults and no clear picture of upcoming capital costs.
Solution: We audited all common-property mechanical assets, rectified the ventilation faults, and set up an annual schedule with reporting formatted for committee meetings and sinking-fund planning.
- · Compliant car park ventilation with documented airflows
- · Clear ten-year capital replacement forecast
- · Reporting the committee can actually read